PMP Exam Formulas and Calculations at a Glance:

You can score perfect on the questions related to following formulas and calculations.

PV = Planned Value
EV = Earned Value
AC =  Actual Cost
CV = Cost Variance
SV = Schedule Variance
CPI = Cost Performance Index
SPI = Schedule Variance Index

CV = EV – AC
SV = EV - PV
CPI = EV/AC
SPI = EV/ PV
BAC = Budget At Completion
EAC = Estimate At Completion
ETC = Estimate Time To Complete
VAC = Variance At Completion

ETC = EAC-AC
VAC = BAC-EAC
Number of Communication Channels
[N (N-1)] / 2
PERT
ET = (P + 4*M + O)/6
Standard Deviation   (P-O)/6

Quality Control
1s = 68.27%
2s = 95.45%
3s = 99.73%
6s = 99.99966%