PMP Exam Formulas and Calculations at a Glance:
You can score perfect on the questions related to following formulas and calculations.
PV = Planned Value
EV = Earned Value
AC = Actual Cost
CV = Cost Variance
SV = Schedule Variance
CPI = Cost Performance Index
SPI = Schedule Variance Index
|
CV = EV – AC
SV = EV - PV
CPI = EV/AC
SPI = EV/ PV
|
BAC = Budget At Completion
EAC = Estimate At Completion
ETC = Estimate Time To Complete
VAC = Variance At Completion
|
ETC = EAC-AC
VAC = BAC-EAC
|
Number of Communication Channels
|
[N (N-1)] / 2
|
PERT
|
ET = (P + 4*M + O)/6
Standard Deviation (P-O)/6
|
Quality Control
|
1s = 68.27%
2s = 95.45%
3s = 99.73%
6s = 99.99966%
|